Meaning
Annealing is heating a plastic part or blank below its melting temperature and cooling it slowly and evenly, so its internal stress relaxes. Mitsubishi describes the aim as a part that is dimensionally predictable. Stock shapes are already annealed by their makers, and Quadrant and Ensinger both say so. A second, intermediate anneal between roughing and finishing is the exception, kept for demanding parts.Trigger Condition
The makers treat annealing after machining as an exception for demanding parts, not a step for every part. Ensinger lists the cases that do. They are narrow tolerances and shapes with a strong tendency to warp, such as asymmetric sections, pockets and grooves. Fiber-reinforced and filled grades are on the list, because fiber orientation can enhance warping. Quadrant adds asymmetric or heavy section changes, with a U-shape from plate and a bush from solid rod as examples. Mitsubishi adds large parts, high material removal and parts that will run at high service temperatures. A symmetric bracket with generous tolerances does not need it. Polycarbonate, polysulfone and PEI are the amorphous grades most often annealed to limit stress crazing. Annealing finished parts becomes more important as machining volume increases. Mitsubishi holds PEI at 200 °C (392 °F).Read More
Rest Alternative
Time at room temperature is the simplest stress relief. Mitsubishi advises roughing large sections and leaving them for 24 hours. Quadrant suggests at least 48 hours in normal ambience before finish machining. A rest needs no oven, only shelf space and a part lying flat and safe. It gives only the relaxation the part can make at room temperature. Ensinger warns that frozen-in stress can reduce suddenly at high service temperature, giving warping or stress cracking. A part that will run hot is therefore a poorer fit for a rest, and the anneal moves that relaxation into the shop.Cycle Timing
Quadrant and Mitsubishi define the cycle by four times. Heat-up runs at 10 to 20 °C (18 to 36 °F) per hour. The hold lasts 10 minutes per millimeter of wall, about 4.2 hours per inch. Cool-down runs at 5 to 10 °C (9 to 18 °F) per hour, and the center then needs 3 minutes per millimeter more. The oven stays within plus or minus 3 °C (5.4 °F) everywhere, at all times. Computed from these rates, a 10 mm (0.39 in) acetal wall at 155 °C (311 °F) spends about 22 to 43 hours in the oven. PEEK at 250 °C (482 °F) takes about 37 to 71 hours. Wall thickness matters far less than hold temperature, because the slow ramps dominate. It allows 4 hours to the hold temperature and a hold of 30 minutes per 6.35 mm (1/4 in). It then cools at 28 °C (50 °F) per hour. For a 10 mm (0.39 in) acetal copolymer wall, those rates sum to about 9.6 hours. The faster cycle trades cooling time for a higher risk of stress built in by uneven cooling. A buyer who sees ten hours on one quote and two days on another asks which cycle each supplier follows.Shape Change
The anneal moves the part, so the program expects it. Quadrant advises at least 3 percent oversize on diameters and lengths of circular parts when pre-machining. It asks for a test on one or a few parts to learn how much the treatment moves. Ensinger notes that annealing can shrink components, so the roughing leaves a safety margin. Parts that tend to bow are fixtured through the whole cycle and stay fixtured until cool to the touch. Quadrant adds that annealing small blocks or thin disks right after cutting them from stock improves stability.Finishing Sequence
Mitsubishi describes the sequence as rough machining, annealing and finish machining with a very light cut, which gives better flatness. The finish machining of critical dimensions comes after the anneal. Quadrant warns that natural-colored parts annealed in air above 100 °C (212 °F) form an oxidized skin, particularly nylon. That skin is usually removed in the finishing pass.Drawing Wording
On a drawing, “heat treated” can mean a stress relief, a post-cure for properties or a drying step. A note that names the purpose, the cycle and the stage lets the supplier schedule the oven days and the finishing pass. Röhm’s separate rule for acrylic, based on sheet thickness, belongs in the same note when the part is acrylic.